Pragmatic Agile Weblog

Agile software development in real life

Stabilization sprints

One of the most advertised advantages of agile development is that at the end of each iteration the product is always releasable. The idea is that each piece of functionality is either done or not done and everything done should be shippable.

Ok, we are not that good yet 🙂 Or maybe this is not even a realistic goal in some organizations or under certain conditions. Under the cover, the subject is not that obvious and if you are interested in knowing more these are few interesting links:

http://blog.mountaingoatsoftware.com/correct-use-of-a-release-sprint

http://www.infoq.com/news/2009/12/stabilization-sprints
http://www.infoq.com/news/2008/02/done-shippable-quality

We adopt stabilization sprints before declaring a release GA. Indeed, the stabilization process is a work-in-progress that we try to improve at every release. For the upcoming release we structured the stabilization process in two main phases: integration and final stabilization. The integration period will take two iterations and is focused on putting all components together and performing integration and other high level testing. Then we will have one iteration of final stabilization. In this last period we will focus on real usage to make sure we do not encounter major issues that will get in the face of the user on real deployments. In the following, the process is described in little more details.

Integration

Length: 2 2week iterations
Focus: integration, regression and performance testing; general testing by selected users (dogfoodding)
Entrance criteria:

  • snapshots of all components ready
  • user documentation ready
  • no bugs targeted to the release
  • no development planned for the release
  • device list of the devices we condider blocker for the release ready

Output: all packages become release candidate

Final stabilization

Length: 1 2week iteration
Focus: stability and general testing by selected users
Entrance criteria:

  • all components are release candidates
  • network environment for testing machines verified and locked
  • performance are ok

Output: all packages become GA

During integration testing any bug found is triaged to determined if it must be fixed in the current release or can be postponed. Of course the bar is pretty high assuming most of the bugs should have been captured during development iterations.
The final stabilization iteration is intended to make sure a live system works smoothly for a period of time without major flaws. In our experience, it is a very good way to capture things that are difficult to foresee in advance and that likely (as per Murphy’s law) a customer would run into pretty soon. Only really sever bugs should block the release at this stage.

I keep asking myself if stabilization sprints are necessary in real cases or instead are just a sign of sub optimal development practices during normal iterations. For now, my experience tells me stabilization gives still a lot of value to the quality of the product shipping and allows to focus the team on tasks that would be not very efficient to do upfront in each iteration. But as usual, we will see how it goes and try to improve next time 😉